Displaying report 1-1 of 1.
Reports until 16:06, Friday 15 March 2013
LHO General
corey.gray@LIGO.ORG - posted 16:06, Friday 15 March 2013 (5820)
Ops DAY Summary

Day's Activities:

Code change for HAM-ISI 2 & 3.  Required re-starting model and DAQ around 10am (Barker, Warner)

Photon Calibrator "dirty" Alignment (Daveloza, Rodruck, Savage)

ISCT1 craned into place by Apollo (west side of HAM1)

Betsy/Travis worked mainly in HAM2

Cyrus doing rackwork in out-buildings

Tour in Control Room around 12:30pm

Crew working on baffle in West Bay cleanroom

RO Alarm toward the end of the day

Dust Alarms: