Keita, Camilla. Follow on from alog 59785. Cable bracket to component SQZ cable status below. Cable document is D1900278. The last cable that attached to the VOPO is #7.
Photos of routing attached, the photos show the cable brackets. Old cable brackets have to be used in some places as the SUS AOSEM cables are old style so do not fit the new brackets.
The plan was to attach all cables to the OPO lid but the cables were stiff enough that it made more sense for some of them to go straight to the SUS support. Cable #11 is cable tied to the OPO, #3 has a secondary cable bracket on the OPO lid, #4 is cable tied to the secondary bracket. #8, #9 go straight to SUS support.
Cable # | Component | Installed | CB (planned) | Comment |
1 | QPD-A | N | n/a | At CIT for assembly. |
2 | QPD-B | N | n/a | At CIT for assembly. |
3 | This cable splits into four. See 3a-d. | Y D2000361 S/N S2101239 | CB-5 1st | |
3a | DCPD-A/B | N | Secondary 1st |
At CIT for assembly. When it arrives it will be plugged into cable bracket D1700307 below DCPD-C/D cable |
3b | DCPD-C/D | Y DCPDs labeled D1600079-V2 003 and 004 | Secondary 2nd | |
3c | Beam Diverter | Y D2000361 S/N S2101239 | n/a | |
3d | VOPO lens translation stage | Y Cable made by Sheila | Secondary on OPO lid | |
4 | VOPO OPO cavity piezos | Y D1700438 S/N S2101231 | CB-5 2nd | |
5 | VOPO SUS AOSEMS (H3,V3) | Y D1000234 S/N S1105081 | old style near CB-6 (CB-6 3rd) | |
6 | Picomotors for SK:BS1, SK:M1 | N | (CB-6 1st) | At CIT for testing, expect next week. |
7 | VOPO Picomotors for H:M1,HM:2, D:M1, D:M2 (D's not VOPO) | N | (CB-6 2nd) | At CIT for testing, expect next week. |
8 | VOPO SFI1 | Y D1700439 S/N S2101235 | CB-5 3rd | |
9 | VOPO SFI2 | Y D1700439 S/N S2101236 | CB-5 4th | |
10 | VOPO SUS AOSEMS (H1,V1, H2, V2) | Y D1000234 S/N 66-910 (?) | old style near CB-4 (CB-4 1st) | |
11 | OPO TEC/Thermistors | Y D1700439 S/N S1700475 | CB-4 1st (CB-4 2nd) |
For ICS assembly see ASSY-D1900278-LHO
Typo above, cable #5 should be D1000239-S1105081
6 | Picomotors for SK:BS1, SK:M1 | D1101516-S2101314 | CB-6 1st |
7 | VOPO Picomotors for H:M1,HM:2, D:M1, D:M2 | D1101516-S2101315 | CB-6 2nd |
Cables #6 and #7 have been installed. We will not plug in SK and D picos until the optics are near their final positions.
The H:M1, H:M2 cables have been routed over the VOPO (see photos 2 and 3). The routing of the H:M2 cable means that CB-6 will need to be closer to the OPOS than expected, nearer the location of the secondary bracket for #3. This shouldn't be a problem as the #5,6,7 flange to CB cables should have plenty of slack to reach. Will check with Jim- tagging SEI.
We had to tilt the L-shaped brackets that hold the pico mighty mouse connectors for H:M1, H:M2 as the optics posts were too short to give the connector enough clearance to point straight down (see photo). This required temporarily removing the black glass clip. We did this carefully so hopefully didn't shift the alignment of the H-path.
VOPO cable routing is now complete. We plan to balance the OPOS today and install the fibers tomorrow (expect minimal change to balancing) if all goes well.
We re-routed the cables before balancing the OPOS (alog 59939) after TJ's advice that having them attached to multiple hard points would have less chance of rubbing.
See photo attached. We now have both SF1 and SFI2 cables (#8,9) going to the H2, V2 post. h1,v1,h2,v2 aosems and OPO TEC (#10,11) to H1, V1 post (as before) and lens translation, OPO peizo, h3,v3 aosems and both pico cables (#3,4,5,6,7) to H3, V3 post (as before).
Adding record of flange to CB cables below.
We decided we need #11 OPO temperature controls next week- once we have the OPO locked in green, use the temperature controls to make sure that the cavity is also resonant for 1064nm. This cable is being sent from CIT and Jim will install it next week. The #6,7,9 cables for picos and SFI2 are going to be at minimum 3+ weeks out. We decided it's okay to install these at the end and test before closing up.
Cable #
|
Component
|
Component to CB Installed?
|
CB to Flange installed?
|
Comment
|
1
|
QPD-A
|
N
|
n/a
|
CIT for He BOM test (Calum 09/23/21).
|
2
|
QPD-B
|
N
|
n/a
|
CIT for He BOM test (Calum 09/23/21).
|
3
|
This cable splits into four. See 3a-d.
|
Y
|
Y
|
|
3a
|
DCPD-A/B
|
N
|
n/a
|
At CIT for clean and bake (Rich 09/24/21)
|
3b
|
DCPD-C/D
|
Y
|
n/a
|
|
3c
|
Beam Diverter
|
Y
|
n/a
|
|
3d
|
VOPO lens translation stage
|
Y
|
n/a
|
|
4
|
VOPO OPO cavity piezos
|
Y
|
Y
|
|
5
|
VOPO SUS AOSEMS (H3,V3)
|
Y
|
Y
|
|
6
|
Picomotors for SK:BS1, SK:M1
|
Y
|
N
|
D1700316 260” being manufactured, expected at CIT next week – will need cleaning and testing (Dean 09/30/21)
|
7
|
VOPO Picomotors for H:M1,HM:2, D:M1, D:M2 (D's not VOPO)
|
Y
|
N
|
D1700316 260” being manufactured, expected at CIT next week – will need cleaning and testing (Dean 09/30/21)
|
8
|
VOPO SFI1
|
Y
|
Y
|
|
9
|
VOPO SFI2
|
Y
|
N
|
D1700316 260” being manufactured, expected at CIT next week – will need cleaning and testing (Dean 09/30/21)
|
10
|
VOPO SUS AOSEMS (H1,V1, H2, V2)
|
Y
|
Y
|
|
11
|
OPO TEC/Thermistors
|
Y
|
N
|
D1700316 120” at CIT being shipped to LHO ready to install (Dean 09/30/21). Jim will install next week.
|
Last week we installed G:PD1 (DCPA-A) and F:PD1 (DCPD-B). All PDs now tested, working and aligned. Still need to be calibrated and H:PD1's BD positon checked.
Cable #
|
Component
|
Installed
|
CB (planned)
|
Comment
|
3a
|
DCPD-A/B
|
Cable S2101245, G:PD1 = S2100023 (D1600079-007 D1600079-007), F:PD1 = S2100024 (D1600079-008 D1600079-008)
|
Secondary CB
|
Has been routed around the -Y, +X side of the OPO
|
Remaining HAM7 SQZ cables are QPDs, Picos, SFI2:
Cable #
|
Component
|
Component to CB Installed?
|
CB to Flange installed?
|
Comment
|
1
|
QPD-A
|
N
|
n/a
|
CIT, shippment to LHO in 2 weeks (Rich 10/15/21).
|
2
|
QPD-B
|
N
|
n/a
|
CIT, shippment to LHO in 2 weeks (Rich 10/15/21).
|
3
|
This cable splits into four. See 3a-d.
|
Y
|
Y
|
|
3a
|
DCPD-A/B
|
Y
|
n/a
|
|
3b
|
DCPD-C/D
|
Y
|
n/a
|
|
3c
|
Beam Diverter
|
Y
|
n/a
|
|
3d
|
VOPO lens translation stage
|
Y
|
n/a
|
|
4
|
VOPO OPO cavity piezos
|
Y
|
Y
|
|
5
|
VOPO SUS AOSEMS (H3,V3)
|
Y
|
Y
|
|
6
|
Picomotors for SK:BS1, SK:M1
|
Y
|
N
|
D1700316 260” being manufactured, expected at CIT next week – will need cleaning and testing (Dean 09/30/21)
|
7
|
VOPO Picomotors for H:M1,HM:2, D:M1, D:M2
|
Y
|
N
|
D1700316 260” - see above
|
8
|
VOPO SFI1
|
Y
|
Y
|
|
9
|
VOPO SFI2
|
Y
|
N
|
D1700316 260” - see above
|
10
|
VOPO SUS AOSEMS (H1,V1, H2, V2)
|
Y
|
Y
|
|
11
|
OPO TEC/Thermistors
|
Y
|
Y - D1700316-S2101403
|
|
This morning Jim and I installed cables #6, 7 and 9 from the roof flange D8 onto the ISI cable brackets.
Cables between cable bracket and component for picomotors SK:BS1, SK:M1, D:M1, D:M2 still need to be connected. This should be done with care so the mirrors aren't bumped- maybe even with laser on to check alignment is kept. The two spare quadrapus cables need to be coiled and secured. Check the pico cable drawing D1101516 and cabling doc D1900278 for which tentacles to connect. ICS ASSY-D1900278-LHO updated.
Cable # | Cable S/N |
6 - Picomotors for SK:BS1, SK:M1 | D1700316-V2-00-S2101661 |
7 - Picomotors for H:M1,HM:2, D:M1, D:M2 | D1700316-V2-00-S2101662 |
9 - VOPO SFI2 | D1700316-V2-00-S2101663 |
Picomotor cables have now been connected to the mirror mounts but not yet tested.
Pico cable | Mirror mount |
#6 Cable 1 (rightmost, near pin25) | SK:BS1 |
#6 Cable 2 | Spare (coiled up with SK:BS1/M1 excess) |
#6 Cable 3 | SK:M1 |
#6 Cable 4 | Spare (coiled up with SK:BS1/M1 excess) |
#7 Cable 1 (rightmost, near pin25) | D:M2 |
#7 Cable 2 | D:M1 |
#7 Cable 3 | H:M2 |
#7 Cable 4 | H:M1 |
To do:
Today I added a dog clamp to CB-6 as needed in alog 61076. It is now secure.
Picomotors were tested and all working, see alog 61505. I swapped SK:M1 from cable 3 to cable 1. This does now not match the D1900278 cable document but matches the actual cabling.