08:00 Dust monitor alarm in EY and EX. Crane cleaning in EY and Apollo working in EX LASER Hazard 09:08 Transition to Laser Safe – Michael R 09:40 DOE start seismic testing in 300 Area near station H3A Dave B updating alarm handler Betsy, Travis, Margo, Kate, and Hugo working in and around HAM 3, HAM2, and BSC2 13:08 DOE stop seismic testing Michael R working with Apollo cleaning in the PSL Enclosure Sheila & Keita move ISCT1 into HAM 2 cleanroom and setup laser safety barriers Filiberto C & Erin pulling in rack cables for BSC3 Filiberto C & Ben A pulling in rack cables at EX for BSC9