HAM5 Schedule snapshot

FYI - Here is a snapshot of the HAM5 task list from the integrated MS Project file showing my estimate of rough percentages of where we are right now on this chamber.  Forgive the formatting as this is a round-about copy paste from the application.  Also, the order may not quite be perfect since this was a suggested order.  We opened HAM5 the 3rd week of Aug, and are nearing closeout in the next week or so.

 

6% 228 HAM5 INSTALL PART 2 (OFI, ZM6, baffles)
47% 229 LOPS - HAM5 CHAMBER OPEN
100% 230 Lock HEPI
100% 231 Clean chamber
100% 232 Open chamber
100% 233 Install work platforms
100% 234 Lock ISI
100% 235 Contam Control Entrance Checks
0% 236 Remove SRM CO2 laser viewport +X door, install blank
0% 237 Swap BOSEMs - refurbish
28% 238 DI - SLiC HAM5 INSTALL
100% 239 Deinstall ZM2TT ZM from -X,-Y side of table, reuse cables for new ZM6
100% 240 Install new cables/D3 flange, up through ISI to new cable table bracket
100% 241 De-Install OFI baffles
100% 242 Laser HAZ: Setup AUX laser on HAM5 and align to center on SR optics, Set irises to capture pointing into OFI
90% 243 Rework OFI with new breadboard, cable up thermistor, picomotors, AOSEMs
80% 244 Ticket 19713 - Cable interference with shroud - sort, doc
100% 245 Cable, test and suspend OFI
100% 246 Install A+ ZM6
80% 247 Cable and test ZM6
80% 248 Install relay mirrors, DCPD path on table, check ghost beam on ZM6
100% 249 Align OFI and ZM6 to HAM6 and HAM7, installing temp Wave plates as needed, align PD path
100% 250 Check OPO beam alignment HAM5 to HAM7
100% 251 Remove AUX laser hardware
50% 252 Reinstall new OFI shroud and baffles, recheck alignment
0% 253 Closeout OFI Tickets 19712, 19713
100% 254 Ticket 9612 - Fix SRM AR Baffle Standoff, add new bottom panels - Not doing
15% 255 Install chamber septum baffle, MCTB snap-on baffles, SR3 baffle, ZM6 baffle
100% 256 Install VPs, FRS 15960, 10452
100% 257 Check alignment of SRM AR Baffle
100% 258 FRS 14623 - SRM CO2 mirror hardware removal
0% 259 FRS 10518 - Fix electrical grounding at TT BOSEMs
0% 260 Rebalance ISI Table
0% 261 Install HAM5 to HAM7 tube nozzle baffle, check for clipping
0% 262 LOPS - HAM5 CHAMBER CLOSEOUT
0% 263 Ticket10037 -Backshell cable grounding mitigtion
0% 264 ground loop hunting
0% 265 Remove ZnSn Viewport from N door, swap with ZV-800
0% 266 View Port inspections
0% 267 First Contact On Optics
0% 268 Robert/Corey photo assay
0% 269 First Contact Off/Top Gun
0% 270 Final Install Baffles
0% 271 perform CC tasks - chamber exit
0% 272 put doors back on
0% 273 take overnight TFs to check for rubbing