Apollo work for 15 April 2013
Crane work continued: snap ring installation on LVEA main crane-one bearing still missing,visual check complete on LVEA East Bay crane and crane released for service,  X End crane making noise so problem-solving is on-going.

Y End: Dis-assembly of Test Stand started. Bolts on BSC6 torqued.

Helped T. Vo needed help with parts, M. Rodruck needed help with PCal assembly, and C. Vorvick needed help with install.