Reports until 08:40, Thursday 25 April 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 08:40, Thursday 25 April 2013 (6200)
HIFO Close-out-LVEA Update
Checklist thru #13 completed before Mark and crew left last night. Major gaps on HAM4 cleanroom closed up.We found a septum blank, O-ring and appropriate fasteners for HAM4. I added a couple of items at the bottom of the list: torquing bolts and looking for holes.

1.	Done-Remove Walking Plates from BSC 2 (Place in E-Mod Staging Cleanroom)
2.	Done-Replace dome on BSC2 (Check with SEI first: unlock ISI check cables)
3.	Done-Place hard cover on BSC2/HAM3 spool openings
4.	Done-Install curtains on HAM3 cleanroom
5.	Done-Move BSC cleanroom to beamtube by East Bay pipe bridge
6.	Done-Dis-assemble Work Platform (Place on floor by ?????)
7.	Done-Move HAM3 cleanroom north as far as possible
8.	Done-Close gaps in cleanroom to contain BSC2 spool area
9.	Done-Move SEI related electronics over center of spool area
10.	Done-Insert small spool piece
11.	Done-Insert large spool piece
12.	Done-Install HAM3 east door
13.	Done-Move cleanroom from pipe bridge area to HAM4-plug in-turn on
14.	Done-Call for HAM4 cleaning
15.	Done-Install HAM2/1 east doors
16.	Done-Install HAM 2/3 west doors
17.	Install BSC1 viewports