There were a couple of items from the list to clear up this morning: torquing of bolts at HAM3 and check to see that all ports have some pump-down worthy covering. In addition, Kyle had a couple of items for the Apollo crew to attend to. I added those items to the bottom of the list. 1. Done-Remove Walking Plates from BSC 2 (Place in E-Mod Staging Cleanroom) 2. Done-Replace dome on BSC2 (Check with SEI first: unlock ISI check cables) 3. Done-Place hard cover on BSC2/HAM3 spool openings 4. Done-Install curtains on HAM3 cleanroom 5. Done-Move BSC cleanroom to beamtube by East Bay pipe bridge 6. Done-Dis-assemble Work Platform (Place on floor by ?????) 7. Done-Move HAM3 cleanroom north as far as possible 8. Done-Close gaps in cleanroom to contain BSC2 spool area 9. Done-Move SEI related electronics over center of spool area 10. Done-Insert small spool piece 11. Done-Insert large spool piece 12. Done-Install HAM3 east door 13. Done-Move cleanroom from pipe bridge area to HAM4-plug in-turn on 14. Done-Call for HAM4 cleaning 15. Done-Install HAM2/1 east doors 16. Done-Install HAM 2/3 west doors 17. Done-Install BSC1 viewports 18. Done-Remove HAM4 north door 19. Done-Install blank on septum plate between BSC2 and HAM4 20. Done-Install HAM4 north door 21. Done-Torque all bolts (except HAM1 and HAM4-4 bolts only) 22. Done-Check for holes 23. Done-Remove the "hinged" HAM4 bellows retraction tie-rods per Kyle 24. Done-Remove, inspect and re-flange (using LIGO hardware) the 10" CFF blank that is in the 2 o-clock position on the MC tube-HAM3 adapter and which is labeled as "not leak tested" per Kyle 25. Done-Return HAM4 bellows tie-rods per John ;-) As far as I know, all Apollo tasks are complete in preparation for HIFO pump-down.