Reports until 12:48, Friday 26 April 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 12:48, Friday 26 April 2013 (6209)
HIFO Close-out-LVEA Update
There were a couple of items from the list to clear up this morning: torquing of bolts at HAM3 and check to see that all ports have some pump-down worthy covering. In addition, Kyle had a couple of items for the Apollo crew to attend to. I added those items to the bottom of the list. 

1.	Done-Remove Walking Plates from BSC 2 (Place in E-Mod Staging Cleanroom)
2.	Done-Replace dome on BSC2 (Check with SEI first: unlock ISI check cables)
3.	Done-Place hard cover on BSC2/HAM3 spool openings
4.	Done-Install curtains on HAM3 cleanroom
5.	Done-Move BSC cleanroom to beamtube by East Bay pipe bridge
6.	Done-Dis-assemble Work Platform (Place on floor by ?????)
7.	Done-Move HAM3 cleanroom north as far as possible
8.	Done-Close gaps in cleanroom to contain BSC2 spool area
9.	Done-Move SEI related electronics over center of spool area
10.	Done-Insert small spool piece
11.	Done-Insert large spool piece
12.	Done-Install HAM3 east door
13.	Done-Move cleanroom from pipe bridge area to HAM4-plug in-turn on
14.	Done-Call for HAM4 cleaning
15.	Done-Install HAM2/1 east doors
16.	Done-Install HAM 2/3 west doors
17.	Done-Install BSC1 viewports
18.	Done-Remove HAM4 north door
19.	Done-Install blank on septum plate between BSC2 and HAM4
20.	Done-Install HAM4 north door
21.	Done-Torque all bolts (except HAM1 and HAM4-4 bolts only)
22.	Done-Check for holes
23.     Done-Remove the "hinged" HAM4 bellows retraction tie-rods per Kyle
24.     Done-Remove, inspect and re-flange (using LIGO hardware) the 10" CFF blank that is in the 2 o-clock position on the MC tube-HAM3 adapter and which is labeled as "not leak tested" per Kyle
25.     Done-Return HAM4 bellows tie-rods per John     ;-)

As far as I know, all Apollo tasks are complete in preparation for HIFO pump-down.