- Apollo "crew" torqued some doors and viewports, and cleared/checked other items, see entry by Jodi.
- Betsy did a walk around input chambers/LVEA area this morning, final check before pump down.
- Michael and Joe, Viewport final check, LVEA, before pump down.
- Travis to work around HAM2 and HAM3, camera work.
- Kyle started pump down of YBM+BSC01+BSC02+BSC03+Inputtube-HAM01, see his entry.
- Keita, et.al., moved/set IOT2L in place.
- Cheryl to LVEA to work in IOT2L.
- King soft water to visit LSB RO system, charcoal work.