Reports until 17:17, Monday 14 March 2011
LHO FMCS
kyle.ryan@LIGO.ORG - posted 17:17, Monday 14 March 2011 (624)
Installed mechanical level guages for CP5 and CP6
Required temporarily depressurizing plumbing supplying CDS level transducers.  

Hope to continue at X-end tomorrow.