H1 TCS
camilla.compton@LIGO.ORG - posted 10:30, Monday 11 April 2022 (62554)
ITMX Ring heater result

We are getting a good ring heater test for ITMX (aligned on Friday alog 62527 and 62530). HWS plot attached here. Now we know the location of ITMX center on the HWS, we can align the CO2X tomorrow.

There is a small amount of coupling into the PROBE_TOTAL_PIXEL_VALUE which shows that there is clipping somewhere. By running Aidan's analyzing matlab script we can see in the attached plots the location of this clipping is bottom left of the beam. When aligning the beam on Friday we saw that this edge was close to clipping. Maybe we can improve the alignment moving away from this clipping point.

Can see that the alignment isn't as good as for ITMY (ring heater test done in alog 62309 and image attached).

Images attached to this report