[Corey, Greg]
Received (3) big plates for the BSC ISI and unloaded at the VPW
Transferred Pitchfork & Boxwork Stage1 Walls from the VPW to Staging Building. Started pre-assembly work on these walls (i.e. pressed dowel pins and inserted helicoils). Assembled (1) Pitchfork (and installed on Stage1 [just pinned to Stage1]).
Moved pallet of HAM-ISI#3 BAD plates out near Fire Water Tank lay down area.