Reports until 15:46, Tuesday 15 March 2011
X1 SEI
corey.gray@LIGO.ORG - posted 15:46, Tuesday 15 March 2011 (627)
ISI Assembly Status

[Corey, Greg]

Received (3) big plates for the BSC ISI and unloaded at the VPW

Transferred Pitchfork & Boxwork Stage1 Walls from the VPW to Staging Building.  Started pre-assembly work on these walls (i.e. pressed dowel pins and inserted helicoils).  Assembled (1) Pitchfork (and installed on Stage1 [just pinned to Stage1]).

Moved pallet of HAM-ISI#3 BAD plates out near Fire Water Tank lay down area.