Reports until 20:53, Thursday 09 May 2013
H1 CDS
cyrus.reed@LIGO.ORG - posted 20:53, Thursday 09 May 2013 (6321)
End Station Switches Connected to Core
(Late Post)

The new edge switches at EX and EY were connected to the core today.  The wireless AP at EY has been moved to the VEA and attached to the new switch - also verified that the signal is still strong in the entry area, so most (all) of the building that needs wireless coverage should have it.  The wireless AP for EX will be installed tomorrow.  Once we have a couple days running experience with the new switches, we will start moving the vacuum and FMCS systems to the new switches in advance of decommissioning the old switches.

(Jumbo frames enabled, IOS 15.0.2SE2 at install.)