H2 INS
corey.gray@LIGO.ORG - posted 16:09, Thursday 17 March 2011 (634)
BSC HEPI Foot Adjustments Started On Next Set

[Corey, Greg, Hugh]

With new numbers, we went about setting the HEPI Foot to their nominal positions prior to installation.  This afternoon we made it through (2) HEPI's.  Tomorrow we'll finish the other two and then start on a HAM set.