H1 INS
jodi.fauver@LIGO.ORG - posted 14:43, Thursday 16 May 2013 (6399)
HAM4 ISI Install Prep
The Apollo crew flew the forklift from the West Bay to the near side of the LVEA so that it would be available to remove doors. Christina and crew took care of second cleaning by ~9:00 am. Then, the Apollo guys started the assembly of the A-frames used in ISI install. There was also some Apollo help on HEPI actuators.