Reports until 15:21, Tuesday 21 May 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 15:21, Tuesday 21 May 2013 (6447)
X End status
Doug and Jason worked on monuments.

The Apollo crew worked on modifying the fourth leg of the Test Stand cleanroom. 

Gerardo and I looked at cleanrooms and space available for cryo-pump baffle assembly and install. The Test Stand cleanroom is big enough for assembly and there appears to be enough room for the Balancing Jig in the BSC cleanroom on the far side of the tube. We will take the precaution of covering the concrete floor in that area with CPStat (to mitigate particulate generation) since it has no vinyl.