thomas.vo@LIGO.ORG - posted 17:03, Wednesday 22 May 2013 (6473)
05/21/2013 Ops Summary
- Bring down HEPI at EY - Hugh
- Doors put back on HAM4 with 4 bols, post ISI installation - Apollo
- Vent EX - Kyle
- Stabilizing ISS in the PSL - Volker & Rick 
- Spool Removal at EX - Apollo
- Remove and replace SUS cables at HAM2- Richard
- Prep for installing the photon calibrator periscope - Rick & crew
- Ellensburg High School visit - Dale