jodi.fauver@LIGO.ORG - posted 07:14, Thursday 30 May 2013 (6554)
ETMX Install Prep
Here is the list that Bubba and I are working from to prep for install.
1.	Disassemble and clean CPB CR FFUs (Jodi and Apollo)-28 May 2013
2.	Complete-Put hard cover on beamtube openings (Apollo)-29 May 2013
3.	Drill holes in Test Stand  for SEI and SUS (Apollo) 28 May 2013-Bubba consulted with Hugh and Betsy
4.	Move BSC CR to BSC5-29 May 2013-Bubba WP-Hugh wants to delay move to BSC9 as long as possible for HEPI actuator work and Apollo needs it out of the way to get the CPB CR into the VEA.
5.	Remove PEM set-up (Michael L.)
6.	Move CPB CR to X End (Apollo)-Begin 28 May 2013: Ceiling framework to X End, Terry S. and Christina apprised of cleaning needs-Cris and Karen cleaned x2
7.	Get Electrical for CPB CR at X End (Richard/Ken)-29 May 2013
8.	Test  CPB CR FFUs (Jodi and Apollo)
9.	Assemble CPB CR over spool (Apollo)
10.	Get BSC ISI and Quad into VEA (SEI/SUS/Apollo)
11.	Install and test leg jacks (Apollo)
12.	Move ISI-CPB jigs/tooling-garbing/staging cleanroom contents-weld equipment/Genie/Ergo Arm-walking plates to X End (Apollo)-28 May 2013-First pass list created and sent to BG-Mick and Zack will work 29 May 2013
CPB-SUS list with pix created 29 May 2013 and given to BG-
13.	Remove ISI Storage container top from building (Apollo)-29 May 2013-BG will take measurements to see whether we can take the lid out later than this.
14.	Move CR from BSC5 to BSC9 (Apollo)
15.	Put CPStat on floor under CPB CR to minimize particulate.
16.	Move E-module and Spiral Staircase into VEA (Apollo)
17.	Remove door from BSC9 for PCal install
18.	Place lower Garbing/Staging CR (Apollo)
19.	Assemble and place E-module including upper garbing/staging cleanroom (Apollo)
20.	Place and level Test Stand (Apollo/IAS)
21.	Clean Test Stand and cleanrooms: CPB, Test Stand, Work Space and lower G/S (Tech Cleaners)
22.	Fly ISI to Test Stand (SEI/Apollo)
23.	Move Test Stand CR over ISI (Apollo)
24.	Get ISI Storage Pallet out of VEA (Apollo)
25.	Place Work Space CR (Apollo)
26.	Week of 10 June 2013
a.	Welding Practice begins (SUS)
b.	Do PCal work at spool (Rick and crew-Apollo help)
-Remove hard cover from spool
-Install-Test-Turn parallel to beamtube
-Close-out check
27.	Marry SUS to ISI (SUS/Apollo)
28.	Level, balance and test ISI (SEI)
29.	SUS check-out (SUS)
30.	Assemble Bosch frame for TMS (before 17 June 2013-nominal date for telescope alignment to begin)-Hardware at VPW
31.	Clean CPB CR (Tech Cleaners)
32.	Move CPB parts into VEA
33.	Assemble CPB and cover (AOS Team) 08 July 2013
34.	Install CPB (AOS Team)
35.	Orient PCal properly (Rick and crew)
36.	Remove dome (Apollo)
37.	Insert ACB Assembly into beamtube thru open BSC door (AOS Team)
38.	Lower BSC cleanroom (Apollo)
39.	Install cartridge (SEI/Apollo)
40.	Raise BSC cleanroom (Apollo)
41.	Install walking plates (Apollo)