Reports until 15:12, Tuesday 04 June 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 15:12, Tuesday 04 June 2013 (6623)
ETMX Install Prep
We continue working away at the long list of items that need to be completed prior to PCal-CPB-ACB-ETMX install. Today, the ISI was moved from the Staging Building to X End VEA using a slow-moving Big Red. The CPB jigs were flown over the LVEA beamtube, loaded onto the trailer, transported to X End and placed in the VEA. See updated list below.


1.	Watch CPB CR particle count trends (Patrick and Michael)-Things look acceptable: 0/0 this morning when I checked. 
2.	Get CPB Jigs and Walking Plates from LVEA to X End VEA (Apollo)
3.	Remove PEM fence etc and tape holes (Apollo)
4.	“Cheat” CPB CR as far towards wall as possible to provide space for CPB Assembly/Install (Apollo)
5.	Cover concrete with CPStat to minimize particulate (Apollo)
6.	Close up hole in CPB CR roof with CPStat or C-3 (Apollo)
7.	Install and test leg jacks on BSC CR (Apollo)
8.	Remove ISI Storage container top from building: move to X Mid-First Bay (Apollo)
9.	Move E-module and Spiral Staircase into VEA (Apollo)
10.	Remove door from BSC9 for PCal install (Apollo)-Put hard cover in place until door is needed by PCal?
11.	Place lower Garbing/Staging CR (Apollo)
12.	Assemble and place E-module including upper garbing/staging cleanroom (Apollo)
13.	Place Test Stand (Apollo/IAS)
14.	Clean Test Stand and cleanrooms: CPB, Test Stand, Work Space and lower G/S (Tech Cleaners)
15.	Fly ISI to Test Stand (SEI/Apollo)
16.	Move Test Stand CR over ISI (Apollo)
17.	Get ISI Storage Pallet out of VEA (Apollo)
18.	Place Work Space CR (Apollo)
19.	Week of 10 June 2013
a.	Welding Practice begins (SUS)
b.	Do PCal work at spool (Rick and crew-Apollo help)
-Remove hard cover from spool
-Install-Test-Turn parallel to beamtube
-Close-out check
20.	Marry SUS to ISI (SUS/Apollo)
21.	Level, balance and test ISI (SEI)
22.	SUS check-out (SUS)
23.	Assemble Bosch frame for TMS (before 17 June 2013-nominal date for telescope alignment to begin)-Hardware at VPW
24.	Clean CPB CR (Tech Cleaners)
25.	Move CPB parts into VEA
26.	Assemble CPB and cover (AOS Team) 08 July 2013
27.	Install CPB (AOS Team)
28.	Orient PCal properly (Rick and crew)
29.	Remove dome (Apollo)
30.	Insert ACB Assembly into beamtube thru open BSC door (AOS Team)
31.	Lower BSC cleanroom (Apollo)
32.	Install cartridge (SEI/Apollo)
33.	Raise BSC cleanroom (Apollo)
34.	Install walking plates (Apollo)