Reports until 15:37, Thursday 06 June 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 15:37, Thursday 06 June 2013 (6656)
ETMX Install Prep
The E-module was assembled and married to the spiral staircase: some transitional plates between the E-mod and the work platform will need to be fabricated and installed when convenient. The Tech Cleaners did the first round of cleaning at BSC9. The Test Stand was craned over the beamtube into position near the roll-up door. Modification of the BSC CR legs to accommodate the leg jacks was started: the ceiling of the CR will be suspended on the crane overnight. The remote control for the crane will be at the corner overnight as a LO-TO measure. All but four bolts were removed from the dome: bolts will come out of the door tomorrow.