Reports until 18:12, Tuesday 11 June 2013
LHO General
patrick.thomas@LIGO.ORG - posted 18:12, Tuesday 11 June 2013 (6701)
Ops Summary
8:42 Praxair delivery
Cleaning at end X
The BSC9 ISI was moved onto the test stand at end X.
10:00 Kiwamu I. transitioned the LVEA to laser safe to allow Filiberto C. to pull power cables to ISCT1. (WP 3966)
11:12 Paradise water delivery
11:59 Mark B. restarted the h1susauxh2 model. (WP 3967)
Cyrus R. and Jim B. went to end Y to connect the reflected memory switch to the corner station. Dave B. changed the IOP models on iscey and lsc0 to turn on the RFM DMA. Chris W. modified the h1iscey and h1lsc models to use the RFM IPC. Dave B. then restarted all the models on these frontends. (WP 3963)
Dave B. reconfigured broadcast0 to add channels to DMT monitoring for HIFO Y. (WP 3961)
12:34 The DAQ was restarted.
1:04 The DAQ was restarted to add Ethercat channels.
1:15 The DAQ was restarted after removing duplicate Ethercat channels.
Kyle replaced a leaking 2.75 CFF gasket on the GV1 plumbing. (WP 3968)
1:37 The DAQ was restarted.
Jim B. went to mid X to remove the IRIG-B from h1pemmx and move the timing signal from the fan-out to the IO chassis. Did not work, reverted to slightly modified original configuration. (WP 3969) (see alog below)
Mark L. went to end Y to see if power cabling needed to be removed tomorrow.
Thomas V. to align the optical levers for ITMY and PR3.
Michael R. transitioned the LVEA to laser hazard.