(Corey, Keita, Lisa, Matt, Virginio)
ISC Table Layout Has Begun
I roughly laid out the QPD Sleds, High Power Beam Dump, & Beam Diverter. Matt & Lisa started laying out all the rest of the optics (which required brining all the hardware from the Corner Station and then building each component, and then laying it out.) Most of the optics are now on the Table. Matt & Lisa will finish off laying them out and then begin aligning everything next week.
Telescope: Staging & Tooling
Virginio & I unwrapped Tooling for suspending the Telescope. Virginio is staging to start using our alignment laser.
Continuing To ICS
Continue to start making Assy Loads and accounting for all parts used for this installation.
EX TMS Weather
Relative Humidity started at 30% in the morning and went to 35% in the afternoon. We will receive desicant packs and hygrometers on Mon/Tues.
TMS Mock Feedthru
Helped Filiberto connect the "roof-side" (vs. lab-side) cables to this Feedthru on Fri as well. We only installed 4 (of 5) cables (5th cable had a bad connector).