H1 PEM (CDS)
filiberto.clara@LIGO.ORG - posted 14:11, Tuesday 02 May 2023 (69257)
Corner Station PEM Upgrades

WP 11121

The following items were completed during today’s maintenance day.

  1. Ran BNC cable from PSL-R2 field rack into PSL enclosure
  2. Ran BNC cable from PSL-R2 field rack to HAM2
  3. Installed Kepco power supply in CER Mezzanine VDD-C5, supply set to 5V
  4. Terminated all 7 microphone power cables with CPC connectors
  5. Attached pigtail cables (CPC to Micro-B) to power cables, verified 5V output
  6. Ran plenum BNC and CAT6 cable from CER to SQZ Bay

Pulling cables from the CER to SQZ Bay took longer than expected. We even enlisted help from VAC group (Gerardo M.) for about an hour. Ran out of time. Following items to be completed next week.

  1. Install new conditioning boxes and microphones
  2. Connect drive signal to audio amps (Corner and Ends) from PEM AI chassis.

F. Clara, A. Helmling-Cornell, G. Moreno, J. Oberling, R. Short