Reports until 11:59, Friday 26 May 2023
LHO General
ryan.short@LIGO.ORG - posted 11:59, Friday 26 May 2023 (69926)
Ops Day Mid Shift Update

We have been making progress towards recovering H1 to full lock. This morning, after running an alignment then manually touching several optics, including walking the beam between PR3 and PR2, we were able to lock DRMI with decent-looking buildups. So far, we've been bypassing DRMI ASC and able to reach DRMI_TO_POP before losing lock. Troubleshooting continues.