H1 AOS
lisa.austin@LIGO.ORG - posted 23:21, Wednesday 10 July 2013 (7046)
SLC - Manifold Cryopump assembly and installation
SLC Team and Apollo

Cleanroom footprint was expanded to the wall (pic 1). 
Weldments, Face Plates and Cylinder were moved into the LVEA (pic 2).
Assembly/Installation Fixture and Balancing Fixture were moved into position (pic 3).
It was identified that the Gate Valve Annulus Piping needs to be removed for installation of baffle (pic 4). This was discussed with John Worden and approved.
Team will begin assembly in the AM after cleanroom has been wiped down and particle count is acceptable.

The large tooling has been at LHO for about two years. The Pusher Brackets which are needed for balancing have not been located. The team will request parts be sent overnite from LLO.
Images attached to this report