patrick.thomas@LIGO.ORG - posted 16:41, Thursday 11 July 2013 (7047)
Ops Summary
Praxair delivered LN2 to the end X cyropump tank.
8:45 Filiberto left to turn on the small clean room between HAM 2 and HAM 3 and pull accelerometer cables. (WP 403) The clean room had been turned off for noise measurements.
~9:00 The small clean room between HAM 2 and HAM 3 was turned on.
9:58 Colin S. and Pablo D. headed out to the H2 PSL enclosure to work on PCAL.
12:39 Jeff B. and Andres headed out to work in the end X TMS lab.
1:09 Dave B. shutdown the h1oaf frontend. (WP 4029)
1:22 Colin S. and Pablo D. left the H2 PSL enclosure for lunch.
2:28 Colin S. and Pablo D. headed out to the H2 PSL enclosure to work on PCAL.
2:45 Corey G. went to the end X lab.
3:15 Dave B. powered down h1fw0 to allow Dan to patch the QFS file system.
3:38 Dave B. powered down the h1iscex frontend to swap its IO chassis.