TITLE: 06/22 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Commissioning
SHIFT SUMMARY:
Lock #1:
Locked for 10:05 when I arrived.
Out of Observing at 17:15 for LSC FF injections LHO:70737, HAM1 FF LHO:70727, ITMY A2L LHO:70730, and PEM work, Jeff also turned off the CAL_AWG_LINES LHO:70724.
Turned on EX wifi for Robert at 19:54, turned it back off when he was done at 20:57 (He also swept the VEA on his exit).
In the CAL_AWG_LINES code, I changed the code so that IDLE is the nominal state so the node will report OK LHO:70736.
Back into Observing at 21:24, out at 22:44 for some more comissioning (MICHFF, more PEM, PSL ISS 2nd loop gain change).
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 16:22 | VAC | Travis | EndY | N | Grab tools from mech room | 16:52 |
| 17:16 | CAL | Gabriele, Elenna | Remote | N | LSC FF injections | 17:58 |
| 17:47 | VAC | Travis, Janos | MidX | N | Mech room | 18:25 |
| 18:08 | CAL | Elenna | Remote | N | ITMY A2L measurement | 18:42 |
| 18:44 | PEM | Robert | CR | N | PEM tests | 20:44 |
| 19:39 | PEM | Robert | EndX | N | PEM tests' | 20:57 |
| 20:58 | CAL | Elenna, Gabriele | Remote | N | FF test | 21:24 |
| 21:50 | VAC | Gerardo | EndY | N | Search for pump parts, valve room | 22:20 |
| 22:44 | CAL | Elenna | Remote | N | MICHFF test | 22:48 |
| 22:45 | PEM | Robert | LVEA | N | Prep measurement | 22:53 |
| 22:53 | PEM | Robert | CR | N | PEM tests | On going |