Reports until 19:12, Monday 15 July 2013
H1 AOS
lisa.austin@LIGO.ORG - posted 19:12, Monday 15 July 2013 (7094)
SLC - Manifold Cryopump assembly and installation
Today's Team - Gerardo Moreno, Mike Vargas and Apollo's Randy and Scott

We bent the Springs (pics 1 and 2) and attached them to the Class B Top ring.
Lifted the baffle and attached it to the Springs at the Flexure Rods (pic 3).
It was very difficult to attach the baffle to the blades because of the tight spacing (pic 4).

Homework for the night - dream about how we can accomplish this task in situ.
The spacing between the Tube Wall and the Baffle is 1.25"; the Rings are 0.5" thick.
There is very little room (0.25") to insert and attach two 1/4-20 nuts with washers.
Images attached to this report