Reports until 17:11, Tuesday 16 July 2013
LHO General
thomas.vo@LIGO.ORG - posted 17:11, Tuesday 16 July 2013 (7103)
07/16/2013 Ops Summary
SLC crew - EX working on Cryopump Baffle

CDS crew - Rebuild of data concentrator - did not work, re-stored to previous working version

Filaberto- Running PEM Cables

Pcal - Working in the H2 PSL Enclosure

Robert - Disconnect dust monitors at ISCT1

Prax Air - Refill CP2

Hugo and Jim W - Taking overnight transfer functions starting at 9 PM PT

Jonathan Hanks - Reconfigure router on GC

Filaberto and crew - Run HAM 5/6 cabling to feed through(s)

Apollo - Install feed through(s) on HAM5/6 and install 16" conflat with new gasket on HAM6