michael.rodruck@LIGO.ORG - posted 16:38, Wednesday 13 April 2011 (711)
H2 PSL installation

Framing of the laser room is nearly complete. They have to finish half of the roof and then they can start installing the sheetrock.

There have been some concerns about dust levels, but a trend of the past three weeks shows that this weeks construction activity has not been abnormally dirty. I plotted dust monitors 9 (2k PSL), 7 (iLIGO HAM8 position), and 5 (beer garden).

Images attached to this report