Displaying report 1-1 of 1.
Reports until 16:25, Monday 29 July 2013
LHO General
thomas.vo@LIGO.ORG - posted 16:25, Monday 29 July 2013 (7275)
07/29/2013 Ops Summary
Remove light pipes from ISCEY - Sheila

Replace check valves at MY and EY - Ski

Hard close GV-18 - Kyle

Soft close GV-5  - Kyle

Relocate the old BSC 10 ISI from termination slab - Apollo

Sweeping both X and Y arms - Stripe Rite

Upgrade all CDS to RCG2.7 - Dave and Jim

Power down all EY CDS computer and networking systems - CDS
Displaying report 1-1 of 1.