H1 PSL (PSL)
corey.gray@LIGO.ORG - posted 06:47, Friday 22 September 2023 - last comment - 07:52, Friday 22 September 2023(73045)
H1 Currently Down Due To PSL

H1 went down a couple of hours ago, and currently see notifications for:

Investigation ongoing.  Have left a voicemail with Jason but he's on vacation;  currently texting with RyanS and will look into restoring High Voltage.

Comments related to this report
corey.gray@LIGO.ORG - 07:06, Friday 22 September 2023 (73047)PSL

As Richard noted, the power glitch appears to have taken down the PSL (NPRO), so it's looking like the PSL will need a complete restart.  RyanS is already getting logged in to assess and Richard will be chatting with him.

corey.gray@LIGO.ORG - 07:23, Friday 22 September 2023 (73048)

According to the ISC_LOCK log the PSL issues are noted at 1107utc (507amPT); Although I just took Observatory Mode to CORRECTIVE MAINTENANCE just a few minutes ago....it should be marked about ~3.5hrs ago (around 342amPT when the first [of 2] power glitches occurred as Richard noted in his alog).

1415UTC (715amPT) STATUS:  RyanS already has the PSL back, IMC is back and H1 started to INITIAL ALIGNMENT.

corey.gray@LIGO.ORG - 07:52, Friday 22 September 2023 (73049)
  • 1450UTC (750AMPT) Initial Alignment COMPLETE
  • Locking Arms Green and begining to get back to NLN.