Reports until 16:51, Thursday 01 August 2013
H1 SEI
hugh.radkins@LIGO.ORG - posted 16:51, Thursday 01 August 2013 (7328)
EndY SEI/HEPI Progress Update
Randy Scott Tyler & Greg; Jim & Keith--Apollo Pipe Fitters

Almost everything is complete for the SEI transfer from BSC6 to BSC10:  All the Actuators are moved, all the plumbing is moved.  One pair of 4-way valves need to be secured to the hardlines.  A piping modification will be made in the mechanical room to give access to the back side of the pump station.  Once that is done, the system can be refilled with fluid for flushing & operation.  Pier electronics can be reinstalled on BSC10...that is about it.
A total of 15 liter of fluid has been removed so far, maybe a little more tomorrow with the MR mod.