Displaying report 1-1 of 1.
Reports until 18:45, Tuesday 19 April 2011
H2 INS
michael.rodruck@LIGO.ORG - posted 18:45, Tuesday 19 April 2011 (739)
H2 PSL installation

Work was started on the interior insulation. Contractors also started work on the floating outer wall but we ran into problems with the drywall screws being too long and touching the inner layer of drywall. They will continue tomorrow with shorter screws.

Dust counts remain normal

Displaying report 1-1 of 1.