Reports until 21:54, Thursday 15 July 2010
X1 SUS
betsy.weaver@LIGO.ORG - posted 21:54, Thursday 15 July 2010 (74)
LHO Q1 Status
BOSEMs were hooked to the EE test stand today.  Signals look live but need calibration before interpretation.  Medm looks to have a nice set of appropriate filter banks for the QUAD controls, but interestingly, does not have a main.adl.  We're also looking to load or rebuild the medm's Brett created for LASTI which have easy to read voltage meters to aid in alignment.  AOSEMs are fresh from the oven and will be installed in the PenRe tomorrow.

The Sleeve was installed onto the QUAD for fit-check today.  It is cumbersome to man handle into place, so we should fiure out a better what to install it...  Clearance holes in the structures could be opened up a bit.