Reports until 10:36, Sunday 05 November 2023
H1 AOS
robert.schofield@LIGO.ORG - posted 10:36, Sunday 05 November 2023 (74005)
1/2 hour commissioning to study CER Air Conditioning coupling

Last night, while LLO was down and before we lost lock, I used 1/2 hour to inject 13.1 Hz ground currents onto the chasis of AC1 in the CER, and also imitated the 13.1 Hz sound AC1 made using the large speaker. Neither the acoustic nor the electronic ground injections produced noise in DARM at the same level as AC1 had.