TITLE: 11/21 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Preventive Maintenance
INCOMING OPERATOR: Corey
SHIFT SUMMARY: Busy maintenance day; SQZ cabling (PMC, OMC), PSL Refcav alignment, ISS 2nd loop, VAC turbopump checks, valves and gauges added to FCT, ALS laser adjustments at EX, HWS work also at EX, cleanroom building at EY, and camera fibers reseeded in the MSR. Back to NLN at 06:00UTC! Lockloss 12 seconds later :(
HAM7 ISI tripped at 17:59 and 18:03 presumably from the SQZ rack work, HAM2 ISI tripped at 18:19 from the measurements being run on HAM2/3. Picket-fence plot died around 18:05 but was able to restart itself after 2 tries and ~5 minutes. Microseism is the highest its been in ~265 days, above the 90th percentile for the past ~12 hours.
Something happened at EndX at 19:29:21, the ISIs state1&2 tripped and so did the HEPI, not sure why, there was no one down there at the time and a DAQ restart was underway. All the sei signals went to zero, the SUS seems fine. After lots of checks and other restarts Erik went down to EX to physically powercycle some chassis, AA, IOP, Fil later joined him, the -18V DC Kepco power supply was found to have failed. FRS ticket 29752, alog74341
21:18 Started to relock
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 16:05 | FAC | Tyler, Chris, Eric | Yarm/FCES | N | Tumbleweed clearing | 16:55 |
| 16:12 | SUS | RyanC | CR | N | ETMY OPLEV Charge measurement | 17:21 |
| 16:14 | FAC | Ibrahim, Randy | LVEA | N | Prep and start Craning | 17:43 |
| 16:16 | TCS | TJ | LVEA | N | TCS cabinets, parts search | 16:29 |
| 16:21 | VAC | Janos | EX, LVEA, Mids, EY | N | Filter bodies for turbo stations | 19:23 |
| 16:21 | EE | Fil | EX | N | SUS HWD checks | 16:51 |
| 16:22 | VAC | Jordan, Gerardo | LVEA/FCES | N | Add valves and gauges to FCT | 19:47 |
| 16:25 | VAC | Travis | MidX, EX | N | Turbopump checks | 19:26 |
| 16:10 | FAC | Karen | EX | N | Tech clean | 16:38 |
| 16:38 | FAC | Karen | EY | N | Tech clean | 17:21 |
| 16:40 | PSL | RyanS, Jason | PSL | N | Ref caf alignment | 19:23 |
| 16:48 | ALS | TJ, Sheila, Dana, Daniel | EX | N | Readjust laser | 17:53 |
| 16:52 | CDS | Dave | Remote | N | Camera work | 17:37 |
| 16:54 | EE | Fil | CER | N | HAM4 ISI coil driver checks | 17:18 |
| 17:16 | FAC | Tyler | 3IFO | N | Checks | 17:33 |
| 17:18 | EE | Fil | LVEA | N | Optical lever measurements | 17:37 |
| 17:27 | FAC | Tyler | Corner | N | Walkthrough with contractors | 18:22 |
| 17:30 | FAC | Karen | LVEA | N | Tech clean, out @ 17:45, back in at 18:05 | 19:19 |
| 17:46 | LAS | EX is LASER HAZARD | EX | Y | EX is LASER HAZARD | 19:29 |
| 17:51 | SQZ | Daniel | SQZ racks | N | Cabling | 18:58 |
| 17:53 | TCS | TJ, Camilla | EX | N | HWS work | 19:23 |
| 17:54 | SEI | Jim | LVEA, HAM1 | N | Take off a piece of foam | 17:58 |
| 17:56 | FAC | Randy, Ibrahim | EY | N | Cleanroom vent prep | 19:48 |
| 17:59 | SEI | Jim | CR | N | HAM2/3 measurements | 19:13 |
| 17:59 | FAC | Cindi | FCES | N | Tech clean | 18:56 |
| 18:04 | EE | Fil | LVEA, SQZ racks | N | Join Daniel with cabling | 18:58 |
| 18:08 | CDS | Jonathon | MSR | N | Camera connections | 19:08 |
| 18:10 | EE | Marc, Fernando | EY | N | Check out cabling | 19:17 |
| 18:23 | FAC | Tyler, Carolyn, Contractor | MidY, EY | N | Walkthrough | 19:42 |
| 18:36 | FAC | Chris +1 | Site | N | Changing locks around site | 20:03 |
| 18:56 | FAC | Cindi | High bay | N | Tech clean | 19:12 |
| 19:12 | FAC | Cindi | OSB receiving | N | Cardboard | 19:24 |
| 19:38 | PSL | RyanS | CR | N | ISS 2nd loop | 20:15 |
| 19:54 | CDS | Erik | EX | N | Powercycle AA, IOP, ... chassis | 20:58 |
| 19:54 | SQZ | Sheila | LVEA | N | OMC cabling | 19:54 |
| 20:02 | OPS | Camilla | LVEA | N | Sweep | 20:18 |
| 20:07 | TCS | TJ | CER then Optics lab | N | Parts search, laptop dropoff | 20:26 |
| 20:20 | EE | FIl | EX | N | Join Erik, checks | 20:58 |
| 21:11 | EE | Fil | EX | N | Bring over a spare power supply | 21:35 |
| 22:57 | VAC | Gerardo, Jordan, Mitchel | LVEA, HAM6 | N | Checks | 23:05 |
I changed the H1:PSL-ISS_REFSIGNAL from -1.97 to -1.98 after we lost lock which brought the Diff power back to tolerance (between 2 and 2.5)