BSCISI #1
Jim is working on prep work for getting parts (mainly hardware such as helicoils, bolts, etc.) Class-A-ed and ready for upcoming work.
BSC Work Area Clean Up
More Small Outer Walls Installed. The Horizontal GS13 Walls were pre-assembled and rest on the Optics Table. We do not have Flexure Access Outer Walls (D071058) available; Hugh assures me that some are currently in a Bake Oven now and could be available in a few days.
Weights have been put on the Walls & on the Optics Table. Now that the innards of HAMISI#3 are being cleared away from both SEI cleanrooms, more and more space is being created for upcoming BSC work!