ETMY Install Prep
The work platform assembly was completed by the Apollo crew. They also transported the balance of the FFUs for the chamber cleanroom from the OSB High Bay to Y end: the FFUs are currently in the outer bay. Hand rails got wiped down and moved into the VEA. Scott worked with Hugh on HAM6 this afternoon.

I spent some time working on the "curtain problem":we have lots of curtains but very few of the correct length for a chamber cleanroom. I think I have a path forward but would like to discuss it with Bubba first.