Displaying report 1-1 of 1.
Reports until 15:04, Tuesday 05 December 2023
H1 PEM
ryan.crouch@LIGO.ORG - posted 15:04, Tuesday 05 December 2023 (74610)
Dust Monitor Quarterly Testing

Closes FAMIS 26614

Ends:

All the end station DMs passed both their zero count and flow tests.

Corner:

All the DMs passed both their zero count and flow tests. The HAM2 DM is still powered off but is working correctly regardless. The PCAL labs (LAB3) dust monitor's channels are not connecting but the DM is working fine. I tried power cycling it but it did not fix the connections issue.

 

The only DMs I didn't get to were PSL 101, and 102 which RyanS will check on the next PSL incursion.