Reports until 10:54, Wednesday 27 December 2023
LHO VE
david.barker@LIGO.ORG - posted 10:54, Wednesday 27 December 2023 - last comment - 13:40, Wednesday 27 December 2023(75051)
Wed CP1 Fill, running with one thermocouple

Wed Dec 27 10:07:13 2023 INFO: Fill completed in 7min 9secs

Gerardo, Richard, Dave:

Gerardo confirmed a good fill curbside.

Gerardo is removing the ice ball at the end of the discharge line which was causing erroneous readings. Currently TC-B is not giving a good value (~1300C). Today's fill ran with TC-A only.

Images attached to this report
Comments related to this report
david.barker@LIGO.ORG - 10:55, Wednesday 27 December 2023 (75052)

I've temporarily bypassed TC-B's cell phone alarms while Gerardo is working on it.

Bypass will expire:
Thu Dec 28 10:19:24 AM PST 2023
For channel(s):
    H0:VAC-LY_CP1_TE102B_DISCHARGE_TEMP_DEGC
    H0:VAC-LY_CP1_TE102B_DISCHARGE_TEMP_DEGC_ERROR
 

gerardo.moreno@LIGO.ORG - 13:40, Wednesday 27 December 2023 (75056)VE

Thermocouple wire for TC-B were spliced together with wire nuts, then some e-tape was used to cover both wire nuts. TC-B is now giving good temperature readings

Filed an FRS ticket to replace thermocouple, 30032