michael.rodruck@LIGO.ORG - posted 16:42, Thursday 21 April 2011 (751)
H2 PSL installation

Lots of work today. The exterior floating wall was completed, as well as the interior insulation on the walls. Supports for HVAC ducting were drilled into the LVEA floor and the enclosure roof. Tomorrow they will be drilling into the roof for ducting.

Dust counts were a bit higher today than the rest of the week, but still no signs of construction affecting the HAM12 clean room.

Images attached to this report