Per the plan, the O4 break was paused today at both LHO and LLO in order to execute a pre-planned list of repairs, maintenance, updates, measurements, and commissioning tasks.
The schedule is shown in the attached PDF and is an estimate based on work loads and task duration.
Today, many preparations were made which push towards venting the isolatable volumes:
Corner chambers
HAM7 chamber
Relay Tube between HAM5 and HAM7
HAM8 chamber
EX
We plan to do inchamber work in HAM6, 7, 3, and 8, and port work on a few different chambers, some at EX.