Reports until 14:27, Thursday 18 January 2024
H1 General
ryan.crouch@LIGO.ORG - posted 14:27, Thursday 18 January 2024 (75462)
OPS Thursday day shift end

TITLE: 01/18 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: HAM6 doors are off, and HAM7 doors are being prepped for removal tomorrow. Jim locked HAM6 around 20:40UTC. Snows picking up and isn't predicted to stop until tomorrow morning.

LOG:                                                                                                                                                                                                                                                                                                                                                                                                                   

Start Time System Name Location Lazer_Haz Task Time End
15:56 FAC Randy LVEA N HAM6, in 15:30-16:00, back in 16:20UTC 20:32
16:24 VAC Jordan, Travis LVEA N Prep for HAM6 door removal!! 20:32
17:00 FAC Chris MidY N Grab tools for fan lubing, then lubing fans 19:33
17:08 CAL Tony & Rick EndX LOCAL PCAL work, TX 21:43
17:30 FAC Kim & Karen LVEA N Tech clean, Kim out at 17:52UTC 18:17
17:34 VAC Gerardo LVEA N Join VAC team 20:32
17:55 EE Ken EndY N Lights 21:22
18:17 FAC Karen Optics lab, Vac prep N tech clean 18:41
19:01 VAC Betsy LVEA, HAM6 N Check out progress 19:20
19:01 FAC Kim, Karen LVEA N Tech clean, Karen in at 19:10UTC 19:53
19:07 SAF Danny Mids, Ends N Safety checks 22:00
19:11 CDS Patrick Remote N Update FMCS code 21:17
19:38 ISC Sheila, Julian Optics lab N Checks 21:03
19:54 ISC Camilla Optics lab N Join Sheila 20:45
20:35 SEI Jim LVEA N Lock HAM6 21:12
20:43 SQZ Vicky Optics lab N SQZ checks 20:54
20:38 FAC Mitch LVEA N Help jim 21:12
20:42 IAS Jason LVEA N Check on the FARO 20:49
21:20 FAC Eric EndX N Investigate heaters Ongoing
21:36 VAC Jordan, Alan, Melena LVEA N Prep HAM7 doors Ongoing
21:41 VAC Gerardo LVEA N Join crew Ongoing

                                                                                                                                                                                                                                                                                                                                                                                                                             

Images attached to this report