Today's activities: - The Annulus volumes of HAM6, HAM7, and GV2 were vented with Nitrogen - HAM6 X+ and X- doors were taken off - HAM7 X+ and X- doors were prepared to be taken off tomorrow - HAM7 RGA electronics was disconnected, the aux cart was removed - The purge air was checked, its quality was satisfactory, see details in comment - The staff left early because of the unpleasant weather conditions So far, everything is going according to plan: https://docs.google.com/spreadsheets/d/1F3Z1cjFrFtaNHayVFVVXruY5JwSiY5-S/edit?usp=sharing&ouid=104962245367404322733&rtpof=true&sd=true
Dewpoint measurement was taken at the output mode cleaner tube purge air output. It was -40.5C and slowly dropping before the dewpoint meter battery decided to die. Since this already satisfied our dewpoint threshold, I did not re-sample after replacing the battery.