TITLE: 01/24 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 4mph Gusts, 2mph 5min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.27 μm/s
QUICK SUMMARY:
- LVEA is laser HAZARD.
- 8am Coordination meeting in the Control Room.
- Return to HAM7 in-chamber work
- EX chamber port work begins at 9am for whole day (Robert)
- Discussion of X-arm burning beginning in Feb.
- EY light work (Ken)
- HAM6 work continues
- Next week LVEA most likely laser SAFE
- FARO work continues
- CO2 laser swap
- HAM3 cleaning needs coordination with Karen/Kim/Chris
- FOMs with ndscopes froze after the DAQ restart yesterday!