TITLE: 01/24 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
- Late Update: (Water leak during TCS laser swap near SQZ table(s))
- EX baffle & TCSx CO2 laser swap work begins.
- OMC (HAM6) alignment in control room & then work on changing balance of OMC, but could not complete due to TCS leak.
- LVEA is now laser SAFE
- EX baffle "in-tube" work complete & ready to seal up EX by VAC.
LOG:
- 1545-1713 EY wind fence prep (randy)
- 1555 LVEA cleaning (karen.kim)
- 1626-1736 EX & MX checks/cleaning (kim)
- 1610-2130 EY lights & EX fiber weld electronics work (ken)
- 1616-1636 Opening HAM5/7 gate valve for HAM7 work (camilla)
- 1621-1633 Grabbing parts in lvea (jordan)
- 1631 MY air handler high temperature alarm (from 65 up to 110degF), notified Tyler.
- 1634-1650 Looking for VAC parts for EX in LVEA (travis)
- 1722 Parts searching again.
- 1636-2130 Escorting Fire Systems contractor to a Mid-Station, Filter Cavity End Station, and OSB (eric.tyler)
- 1651 CO2x Laser swap work (camilla, tj, jason, ryanS)
- 1837-1855 Coffee break!
- 2015-2134 lunch break
- 1706-1722 LVEA Output Tube dewpoint measurment (jordan)
- 1715-1718 LVEA checks (mitch)
- 1730 EX Baffle work (robert, mitch, VAC team)
- lunch break
- 2329 inside work complete!
- 2329 VAC needs to start sealing up.
- 1730 EX rga work (VAC team)
- 1749 lvea crane prep work (randy)
- 1805-1840 EX check of fiber welding recepticle (richard)
- 1820-1840 Working with TCS team (karen)
- 1850-1920 Checking up on EX work (betsy)
- ?? - 1952Finishing up aligning of OMC from Control room (Keita, Koji, Rahul)
- 1950-2052 SQZT0 photos (daniel, vicky)
- 2049-2323 OMC re-balancing (koji, keita, dana, rahul)
- 2052-2117 Continuing prep for moving items in lvea (randy)
- ? - 2324 EX Baffle afternoon work (robert, mitch)
- 2135-2157 MY to pick up parts (marc, jabari)
- 2211 Checking HAM6 work (betsy)
- 2227 TCS Water leak around Squeezer table (tj notified control room)
- A "Stop Work" is currently in effect due to this & Mike (& involved parties) will start composing the documentation for this.
- 2238 Checking on LVEA work (richard)
- 2240 LVEA Transitioned to Laser SAFE
- 2300 Checking on LVEA activities (mike)
- 2302-2315 Checking on state of Squeezer (daniel.sheila.vicky.naoki)