So far, the O4 break vent & commissioning work is proceeding as planned, with only minor hiccups. Yesterday's TCS water leak caused a pause to the HAM6 in-chamber OMC alignment work, but we were able to resume this morning pretty quickly with only a short amount of time down.
The attached snapshot shows the planned schedule outline with green checkmarks next to the items completed so far on the left hand side. On the right is a running log of the activities which have taken place daily (for ease of viewing all in one place).
Teams currently on: