Reports until 20:11, Thursday 25 January 2024
H1 SYS
betsy.weaver@LIGO.ORG - posted 20:11, Thursday 25 January 2024 - last comment - 09:21, Thursday 01 February 2024(75564)
Vent work progress update

So far, the O4 break vent & commissioning work is proceeding as planned, with only minor hiccups.  Yesterday's TCS water leak caused a pause to the HAM6 in-chamber OMC alignment work, but we were able to resume this morning pretty quickly with only a short amount of time down.

The attached snapshot shows the planned schedule outline with green checkmarks next to the items completed so far on the left hand side.  On the right is a running log of the activities which have taken place daily (for ease of viewing all in one place).

Teams currently on:

 

Non-image files attached to this report
Comments related to this report
betsy.weaver@LIGO.ORG - 14:26, Friday 26 January 2024 (75582)
Images attached to this comment
corey.gray@LIGO.ORG - 09:21, Thursday 01 February 2024 (75666)EPO

Tagging EPO for FARO Alignment, baffle, Output Mode Cleaner photos.