Late entry. Activities at 1-25: - The RGA was completely rebuilt at EX, and the RGA tree was already leak checked. Currently it is pumped, and it is already at the E-9 Torr region - The 12" 3IFO feedthrough was replaced with a blank on BSC5 at EX - The spare roughing stations were completely finished So far, everything went as scheduled.